Rampion Offshore Wind Farm Boulder Relocation

We performed a large-scale boulder relocation campaign on the Rampion Offshore Wind Farm. 

We performed a large-scale boulder relocation campaign on the Rampion Offshore Wind Farm. 

Using the FS Pegasus and Edda Fonn, we relocated 16,000 boulders using Tine Grab tooling and rock bag installation. The scope of work required simultaneous boulder relocation and seabed survey, and we recorded as left multibeam bathymetry and video survey data. Our team relocated more than 80 boulders per day on average throughout the project.

16000

boulders relocated

80

boulders cleared a day

2

vessels mobilised

DNVAssociation of Diving ContractorsIMCAInstitute of Explosives EngineersAchilles UVDB - Silver PlusAchilles Oil and Gas Europe - SilverAchilles UNCE - Silver PlusLloyds Register Approved Service SupplierConstructionline - Gold Member